Tropicana comprises a series of open pits and an underground mine located 200km east of Sunrise Dam and 330km east-northeast of Kalgoorlie in Western Australia.
Key metrics FY24
Ownership
70%
Regis Resources Ltd (30%)
Mineral Reserve
1.35
million ounces of gold
Gold production
313,000
ounces
All-in sustaining costs
1,297
US$ per ounce
Capital expenditure
88
US$ million
Workforce
1,010
including contractors
Tropicana is a joint venture between AngloGold Ashanti Australia Ltd (70%), which manages the operation, and Regis Resources Ltd (30%).
Tropicana is a large open-pit operation, with a growing underground mining component, after development of the site’s first underground mine beneath the Boston Shaker pit in mid-2020. Open pit and underground mining are carried out by Macmahon under an alliance contract. Open pit mining uses conventional drill and blast and load and haul methods, while underground mining uses jumbo development and mechanised open stoping. Since start-up, ore has been sourced from the Tropicana, Havana, Havana South and Boston Shaker pits. The Boston Shaker pit is currently the main source of open cut ore while a major cutback of the Havana pit is carried out. Open pit material will be supplemented by approximately 1.2 Mtpa of ore mined from the Boston Shaker underground mine, and stockpiles.
The Tropicana processing plant achieved throughput capacity of between 8-9 Mtpa following several upgrades, including the installation of a second ball mill. The processing plant comprises a three-stage crushing circuit, inclusive of energy-efficient high-pressure grinding rolls, followed by conventional ball mill grinding and CIL recovery.
A brief history
- Open pit mining began during 2012 with first gold produced in September 2013
- After a positive feasibility study, underground mining began at Boston Shaker in 2019
- Tropicana reached the 3Moz production milestone in the first quarter of 2020
- First stoping in the Boston Shaker underground mine took place in June 2020 with the mine achieving commercial production in September 2020
- On 22 April 2021, Regis Resources acquired IGO’s 30% stake in Tropicana
- Ore production from the Tropicana underground mine began in 2022
- The Havana underground mine was approved in 2024 and portal development began in September that year
- Construction of a renewable energy facility, which began in the second half of 2023, was completed on schedule in early 2025. The facility will integrate 61MW of clean solar and wind energy into Tropicana’s existing gas fired power system, reducing the site’s diesel and gas consumption for power generation by 96% and 50% respectively, and slashing carbon emissions by more than 65,000t annually over the next decade
For further information
- Mineral Resource and Mineral Reserve Report 2024
PDF, 8MB - Annual Report 2024: Regional reviews
PDF, 4.62MB - Operational Profile 2024: Tropicana
PDF, 2.5MB



